Don't forget to check out the Construction Updates page for floor plans, renderings, and video tours inside and outside the new building.
Monday, April 11th 2011
Bidding Opportunities
• Early Sitework, Utilities, and Partial Building Demolition [pdf]
• Phase 1 Asbestos Hazard Abatement & Related Work, Including UST System Removal [pdf]
Friday, February 11th 2011
Bidder's Interest Meeting
Information about the project, including bid dates and bid packages can be found here.
Tuesday, January 11th 2011
Updated Planning Timeline
Approve Schematic Design - December 2010
Approve Phasing Schedule - January 2011
Selecting Testing and Balancing Agent - January 2011
Select Maintenance Plan Advisor - February 2011
Bidder Interest Meeting - February 2011
Begin Moving Dirt - mid April 2011
Ground Breaking Ceremony - May 2011
Asbestos Removal - Summer 2011
Demolition of selected areas of high school - Summer 2011